search: 
Description Client Start Date Period Amount
REHABILITATION OF SECTIONS OF TRUNK ROAD 23 SECTION 3 BETWEEN PORTERVILLE (KM 36.9) AND PIKETBERG (KM 60.6)
DEPARTMENT OF TRANSPORT AND PUBLIC WORKS, WESTERN CAPE GOVERNMENT
06/09/2016
18  Months
R 169 725 206.56
THE RESURFACING OF NATIONAL ROAD R518 SECTION 1 FROM LEPHALALE (KM 0.0) TO MMATLADI (KM 38.0) AND FROM MMATLADI (KM 38.0) TO MARKEN (KM 70.7)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
02/09/2016
8  Months
R 119 575 228.14
THE RESURFACING OF NATIONAL ROUTE N12 SECTION 15 FROM WOLMARANSSTAD (KM 0,00) TO JAKKALSFONTEIN (KM 45,80) AND FROM JAKKALSFONTEIN (KM 45,80) TO KLERKSDORP (KM 76.40)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
01/09/2016
8  Months
R 95 997 786.90
THE RESURFACING OF NATIONAL ROAD R30 SECTION 7 FROM VAALRIVIER (KM 0,0) TO KLERKSDORP (KM 14,5)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
01/09/2016
8  Months
R 54 991 316.58
THE RESURFACING OF THE NATIONAL ROAD R503 SECTION 2 FROM COLIGNY (KM 0) TO LICHTENBURG (KM 21.8) AND R505 SECTION 5 FROM N14 (KM 0) TO LICHTENBURG (KM 27)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
01/09/2016
8  Months
R 59 882 535.60
THE RESURFACING OF THE NATIONAL ROADS D1120, D2683, D2948 & D797 IN THE KOMATIPOORT AREA (66.93 KM)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
01/09/2016
9  Months
R 76 360 995.06
UPGRADING OF AN EXISTING C-MAX FACILITY INTO A HIGH DETENTION SECURITY FACILITY (COMPLETION OF PROJECT)
DEPARTMENT OF PUBLIC WORKS, REPUBLIC OF SOUTH AFRICA
19/07/2016
24  Months
R 169 988 000.00
PERIODIC MAINTENANCE ON NATIONAL ROUTE 2 SECTION 25, FROM EB CLOETE INTERCHANGE (KM 17.0) TO MT EDGECOMBE INTERCHANGE (KM 30.8)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
19/07/2016
21  Months
R 106 888 936.39
PERIODIC MAINTENANCE ON NATIONAL ROUTE N2 SECTION 16 FROM R63 KOMGA I/S (KM 70,2) TO KEI RIVER (KM 80,6)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
18/07/2016
10  Months
R 90 350 000.01
SUBCONTRACT: SOLAR FIELD FOUNDATIONS OF ONE HALF (50%) OF THE SOLAR FIELD
LICIASTAR (PTY) LTD
14/07/2016
6  Months
R 102 853 285.20
RECONSTRUCTION OF THE SAND RIVER BRIDGE
DEPARTMENT OF ROADS AND PUBLIC WORKS: EASTERN CAPE
01/06/2016
15  Months
R 57 545 404.59
THE APPOINTMENT OF CONTRACTORS FOR THE UPGRADE OF FEEDER AND COMPLEMENTARY ROUTES AND THE CONSTRUCTION OF BUS STOPS AND RELATED INFRASTRUCTURE FOR PHASE 1 PF THE EKURHULENI IRPTN ON AN AS AND WHEN REQUIRED BASIS FROM 1 JULY 2015 UNTIL 30 JUNE 2018
EKURHULENI METROPOLITAN MUNICIPALITY
17/05/2016
26  Months
R 94 722 600.00
THE CONSTRUCTION OF 15 BUILDINGS RDP BUILDINGS 480 UNITS ON RIVERSIDE VIEW EXTENSION 32, DIEPSLOOT
VALUMAX NORTHERN FARMS (PTY) LTD
21/04/2016
20  Months
R 76 038 920.75
SAFETY IMPROVEMENTS ON MAIN ROAD 139/2 EDGEHILL - SWEETWATERS FROM KM 0.000 TO KM 5.020
PROVINCE KWAZULU-NATAL DEPT TRANSPORT
08/04/2016
8  Months
R 52 322 190.00
THE WIDENING OF STRUCTURES ON NATIONAL ROUTE 10 SECTION 11 BETWEEN GROBLERSHOOP (KM 0.00) AND UPINGTON (KM 115.53)
SANRAL
01/03/2016
12  Months
R 65 355 407.00
UPGRADING OF MDC SECTION 15A (N4-8X) FROM HECTORSPRUIT (KM 38.83) TO KOMATIPOORT (KM 63.46)
TRANS AFRICAN CONCESSIONS
17/02/2016
18  Months
R 269 264 910.00
PERIODIC MAINTENANCE ON NATIONAL ROUTE 2 BETWEEN SECTION 26, UMHLOTI (KM 13.7) AND SECTION 27, NEW GUELDERLAND (KM 33.0)
SANRAL
12/02/2016
15  Months
R 88 725 000.00
THE PARTIAL RECONSTRUCTION OF NATIONAL ROAD R23 SECTION 1 FROM VOLKSRUST TO KM 30
SANRAL
11/01/2016
21  Months
R 175 666 000.00
THE REHABILITATION OF DR2963 AND MR739 FROM THE NATIONAL ROUTE 7 (N7) TO HONDEKLIPBAAI-PHASE 2 - KLIPFONTEIN (km12.0) TO MR739 (km 19.8)
PROVINCE NORTHERN CAPE
25/11/2015
12  Months
R 89 925 800.00
RESURFACING ON NATIONAL ROUTE R67 SECTION 4 FROM SEYMOUR (KM 0.00) TO WHITTLESEA (KM 54.44)
SANRAL
01/11/2015
14  Months
R 166 500 000.00
LESEDI PRIVATE HOSPITAL - SOWETO - PHASE 1
CLINIX HEALTH GROUP LIMITED
01/10/2015
12  Months
R 135 298 000.00
THE RESEAL OF TRUNK ROAD 77 SECTION 1 FROM YZERFONTEIN (KM 71.41) TO LANGEBAAN (KM 111.45)
WESTERN CAPE GOVERNMENT: TRANSPORT AND PUBLIC WORKS
24/08/2015
9  Months
R 86 286 000.00
THE MAINTENANCE AND REHABILITATION OF THE FOLLOWING SECTIONS OF THE MAPUTO DEVELOPMENT CORRIDOR: PART 1: REHABILITATION OF PART OF MDC SECTION 1 FROM KM 0,0 (SPITSKOP) TO KM 14,80 (HIGHVELD I/C) (N4-3) PART 2: MAINTENANCE OF MDC SECTION 2F FROM KM 46,
TRANS AFRICAN CONCESSIONS (PTY) LTD
14/08/2015
12  Months
R 205 296 448.44
REHABILITATION OF MAIN ROAD 107 (YELLOWWOOD DRIVE FROM KM 0,0 TO KM 15,75 - KWADUKUZA)
PROVINCE KWAZULU-NATAL
14/08/2015
12  Months
R 86 888 000.00
THE REHABILITATION OF THE N3 TOLL ROAD PART 1: BETWEEN VAN REENEN (KM 0,0) AND BLACKSPRUIT (KM 24,0) 24,0KM) (HIGHWAY SECTION 12XB AND 13X) PART 2: BETWEEN BLACKSPRUIT (KM 24,0) AND HARRISMITH SOUTH I/C (KM 29,1) (5,1KM) (HIGHWAY SECTION 14XA) PART 3:
N3 TOLL CONCESSION (PTY) LTD
31/07/2015
16  Months
R 182 263 227.36
 