Description Client Start Date Period Amount
UPGRADING OF AN EXISTING C-MAX FACILITY INTO A HIGH DETENTION SECURITY FACILITY (COMPLETION OF PROJECT)
DEPARTMENT OF PUBLIC WORKS, REPUBLIC OF SOUTH AFRICA
19/07/2016
24  Months
R 169 988 000.00
PERIODIC MAINTENANCE ON NATIONAL ROUTE 2 SECTION 25, FROM EB CLOETE INTERCHANGE (KM 17.0) TO MT EDGECOMBE INTERCHANGE (KM 30.8)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
19/07/2016
21  Months
R 106 888 936.39
PERIODIC MAINTENANCE ON NATIONAL ROUTE N2 SECTION 16 FROM R63 KOMGA I/S (KM 70,2) TO KEI RIVER (KM 80,6)
THE SOUTH AFRICAN NATIONAL ROADS AGENCY SOC LIMITED
18/07/2016
10  Months
R 90 350 000.01
SUBCONTRACT: SOLAR FIELD FOUNDATIONS OF ONE HALF (50%) OF THE SOLAR FIELD
LICIASTAR (PTY) LTD
14/07/2016
6  Months
R 102 853 285.20
RECONSTRUCTION OF THE SAND RIVER BRIDGE
DEPARTMENT OF ROADS AND PUBLIC WORKS: EASTERN CAPE
01/06/2016
15  Months
R 57 545 404.59
THE APPOINTMENT OF CONTRACTORS FOR THE UPGRADE OF FEEDER AND COMPLEMENTARY ROUTES AND THE CONSTRUCTION OF BUS STOPS AND RELATED INFRASTRUCTURE FOR PHASE 1 PF THE EKURHULENI IRPTN ON AN AS AND WHEN REQUIRED BASIS FROM 1 JULY 2015 UNTIL 30 JUNE 2018
EKURHULENI METROPOLITAN MUNICIPALITY
17/05/2016
26  Months
R 94 722 600.00
THE CONSTRUCTION OF 15 BUILDINGS RDP BUILDINGS 480 UNITS ON RIVERSIDE VIEW EXTENSION 32, DIEPSLOOT
VALUMAX NORTHERN FARMS (PTY) LTD
21/04/2016
20  Months
R 76 038 920.75
SAFETY IMPROVEMENTS ON MAIN ROAD 139/2 EDGEHILL - SWEETWATERS FROM KM 0.000 TO KM 5.020
PROVINCE KWAZULU-NATAL DEPT TRANSPORT
08/04/2016
8  Months
R 52 322 190.00
THE WIDENING OF STRUCTURES ON NATIONAL ROUTE 10 SECTION 11 BETWEEN GROBLERSHOOP (KM 0.00) AND UPINGTON (KM 115.53)
SANRAL
01/03/2016
12  Months
R 65 355 407.00
UPGRADING OF MDC SECTION 15A (N4-8X) FROM HECTORSPRUIT (KM 38.83) TO KOMATIPOORT (KM 63.46)
TRANS AFRICAN CONCESSIONS
17/02/2016
18  Months
R 269 264 910.00
PERIODIC MAINTENANCE ON NATIONAL ROUTE 2 BETWEEN SECTION 26, UMHLOTI (KM 13.7) AND SECTION 27, NEW GUELDERLAND (KM 33.0)
SANRAL
12/02/2016
15  Months
R 88 725 000.00
THE PARTIAL RECONSTRUCTION OF NATIONAL ROAD R23 SECTION 1 FROM VOLKSRUST TO KM 30
SANRAL
11/01/2016
21  Months
R 175 666 000.00
THE REHABILITATION OF DR2963 AND MR739 FROM THE NATIONAL ROUTE 7 (N7) TO HONDEKLIPBAAI-PHASE 2 - KLIPFONTEIN (km12.0) TO MR739 (km 19.8)
PROVINCE NORTHERN CAPE
25/11/2015
12  Months
R 89 925 800.00
RESURFACING ON NATIONAL ROUTE R67 SECTION 4 FROM SEYMOUR (KM 0.00) TO WHITTLESEA (KM 54.44)
SANRAL
01/11/2015
14  Months
R 166 500 000.00
LESEDI PRIVATE HOSPITAL - SOWETO - PHASE 1
CLINIX HEALTH GROUP LIMITED
01/10/2015
12  Months
R 135 298 000.00
THE RESEAL OF TRUNK ROAD 77 SECTION 1 FROM YZERFONTEIN (KM 71.41) TO LANGEBAAN (KM 111.45)
WESTERN CAPE GOVERNMENT: TRANSPORT AND PUBLIC WORKS
24/08/2015
9  Months
R 86 286 000.00
THE MAINTENANCE AND REHABILITATION OF THE FOLLOWING SECTIONS OF THE MAPUTO DEVELOPMENT CORRIDOR: PART 1: REHABILITATION OF PART OF MDC SECTION 1 FROM KM 0,0 (SPITSKOP) TO KM 14,80 (HIGHVELD I/C) (N4-3) PART 2: MAINTENANCE OF MDC SECTION 2F FROM KM 46,
TRANS AFRICAN CONCESSIONS (PTY) LTD
14/08/2015
12  Months
R 205 296 448.44
REHABILITATION OF MAIN ROAD 107 (YELLOWWOOD DRIVE FROM KM 0,0 TO KM 15,75 - KWADUKUZA)
PROVINCE KWAZULU-NATAL
14/08/2015
12  Months
R 86 888 000.00
THE REHABILITATION OF THE N3 TOLL ROAD PART 1: BETWEEN VAN REENEN (KM 0,0) AND BLACKSPRUIT (KM 24,0) 24,0KM) (HIGHWAY SECTION 12XB AND 13X) PART 2: BETWEEN BLACKSPRUIT (KM 24,0) AND HARRISMITH SOUTH I/C (KM 29,1) (5,1KM) (HIGHWAY SECTION 14XA) PART 3:
N3 TOLL CONCESSION (PTY) LTD
31/07/2015
16  Months
R 182 263 227.36
SUBCONTRACT: THE REHABILITATION OF THE N1 TOLL ROAD BETWEEN BELA-BELA AND POLOKWANE
BBP II JOINT VENTURE
30/07/2015
9  Months
R 61 209 293.33
THE REHABILITATION OF MAIN ROAD P47-3 LIGHT REHABILITATION BY ASPHALT OVERLAY FROM (KM 29.000 TO KM 47.500)
DEPARTMENT TRANSPORT: PROVINCE OF KWAZULU-NATAL
22/07/2015
6  Months
R 56 615 059.31
RACEWAY PARK HOUSING DEVELOPMENT - PHASE 2 - CONSTRUCTION OF HOUSES IN RACEWAY PARK DEVELOPMENT BLOEMFONTEIN EXT 226
Ontrack Professional Construction Project Management
20/07/2015
10  Months
R 42 642 295.99
THE RESURFACING OF NATIONAL ROAD R34 SECTION 1 FROM VRYBURG (KM 0,0) TO KM 31,0
SANRAL
14/07/2015
10  Months
R 68 416 207.38
THE SPECIAL MAINTENANCE OF NATIONAL ROUTE N2 SECTION 11 FROM BRAMLIN INTERCHANGE (KM 22.7) TO SOUTWERKE (KM 50.7)
SANRAL
01/07/2015
18  Months
R 198 310 000.00
UPGRADING OF ROAD DR08029 WILD COAST MEANDER (PHASE 1) TOMBO TO ISILIMELA HOSPITAL 17KM CONTRACT B
DEPARTMENT OF RAODS AND PUBLIC WORKS EASTERN CAPE
18/05/2015
24  Months
R 222 160 991.80
 